Document
Document
  • Related documents Related
  • Full details Details
  • Report document? Report?
?

Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.

Date recorded as the time of writing.

Date of document

15/11/1945

The year in which a vessel’s construction is completed.

Year of ship completion

1945

The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.

Shipbuilder

Yarrows Ltd

The port or place in which the vessel’s construction took place, at the time of writing.

Place of build

Esquimalt, British Columbia

Abbreviations of the names of ports with Lloyd’s Register survey offices.

Port of survey abbreviations

Vcr

Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.

Document identity

1 Steel Steamer or Motorship

The date of first visit by a surveyor.

Date of first survey

02/07/1946

The individual and/or organisation listed

Ship owner

Admiralty

Location where the document is written.

Location of Document Creation

Vancouver

Location where a vessel’s survey was undertaken.

Location of Survey

Vancouver

Date of the meeting of the Classing Committee.

Date of Classing committee

01/01/1948

Broad categories and subdivisions of vessels related to their purpose or function.

Ship type

Landing Ship, Tank

Predominant material(s) utilised in a vessel’s construction.

Material of construction

Steel

A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).

Gross Register Tonnage

4290

Tonnage derived by deducting from the gross register tonnage the capacity that in unavailable for cargo, e.g. machinery space, fuel, crew accommodation etc.

Net Register Tonnage

2430

Is machinery fitted at the aft of the vessel?

Machinery aft?

No

Generally a smaller additional auxiliary boiler (often used while the vessel is at port).

Is a donkey boiler fitted?

No

Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.

Lloyd's Proving House?

No

Also referred to as extreme breadth. The distance from the extreme starboard side to the extreme port side.

Registered Beam

54.1

Physical extent of a record.

Number of parts

2

Name of ship as recorded on the record

Ship name

L.S.T. 3534 - 1945

The process of transferring a vessel to water, but not necessarily her completion.

Launch Date

06/11/1946

Unique identifier for a given ship, it is assigned by a builder.

Yard no

54

The country in which the vessel’s construction took place, at the time of writing.

Country of build

Canada

Unique internal numbers used for identifying, referring and retrieving a specific survey report.

Survey number

6727

Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.

First entry?

Y

The date of last visit by a surveyor.

Date of latest survey

11/08/1945

Name of the individual/entity/organisation responsible for authoring the record

Document author

D S Forsyth

Name of surveyor.

Surveyor

Douglas Skinner Forsyth

Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.

Classification

+A- for Government service

Recorded information related to a vessel’s movements.

Voyage information

Vancouver, British Columbia

A vessel’s means of propulsion.

Propulsion

Steam

Is the steamer assisted by sail?

Sail assisted steamer

No

A ship’s total internal capacity of a ship measured in register tons from the top of the floors to the tonnage deck.

Under Deck Tonnage

4054

Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.

Refrigeration machinery fitted for cargo purposes?

No

Does the vessel possess an auxiliary power source?

Auxillary

No

Is electric lighting fitted to the vessel?

Electric light fitted?

No

Prescribed by flag/registration authorities, and usually excludes a small part of the stern. It is measured from the foreside of the stern at the extreme top to the afterside of the stern post.

Registered Length

330.6

Measurement from the underside of the upper deck on the centre line to the upper side of the bottom plating.

Registered Depth

27.1

Report an issue with this document

Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.