Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
15/10/1963
The year in which a vessel’s construction is completed.
1963
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Mitsubishi Shipbuilding & Engineering Co Ltd
Unique identifier for a given ship, it is assigned by a builder.
H 161
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Hma
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
13 Report on Electrical Equipment
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The date of last visit by a surveyor.
03/10/1963
Name of the individual/entity/organisation responsible for authoring the record
J E Radcliffe; K Okada
Location where a vessel’s survey was undertaken.
Hiroshima
Date of the meeting of the Classing Committee.
14/02/1964
A vessel’s means of propulsion.
Motor (internal combustion)
Is the steamer assisted by sail?
No
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
Physical extent of a record.
2
Name of ship as recorded on the record
Likhoslavl
The process of transferring a vessel to water, but not necessarily her completion.
22/05/1963
Name of the shipbuilder as it appears on the record.
Y Kaneda
The port or place in which the vessel’s construction took place, at the time of writing.
Hiroshima
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
3008
The listed port to which a given vessel belongs.
Odessa
The date of first visit by a surveyor.
20/05/1963
The individual and/or organisation listed
V/O Sudoimport U S S R
Location where the document is written.
Hiroshima
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
See Rpt 1
Broad categories and subdivisions of vessels related to their purpose or function.
Tanker
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
22371
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Have you noticed missing or incorrect data or images for this document?