Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
05/07/1923
The year in which a vessel’s construction is completed.
1889
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Barclay, Curle & Co Ltd
The port or place in which the vessel’s construction took place, at the time of writing.
Whiteinch, Glasgow
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
Name of the individual/entity/organisation responsible for authoring the record
Assistant to the Secretary, Lloyd's Register; C H L Pilditch
Broad categories and subdivisions of vessels related to their purpose or function.
Cargo
A vessel’s means of propulsion.
Sail
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
2126
Tonnage derived by deducting from the gross register tonnage the capacity that in unavailable for cargo, e.g. machinery space, fuel, crew accommodation etc.
1994
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Pertinent, useful or interesting recorded content.
Mr A Gillant has stated to the surveyors in Antwerp that the demolition has commenced. Answer references the attachment of AI AL WR CV 1919 - 1940 380
Name of ship as recorded on the record
Glaucus
The process of transferring a vessel to water, but not necessarily her completion.
13/03/1889
Unique identifier for a given ship, it is assigned by a builder.
355
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
Memo
The individual and/or organisation listed
Mr A Gillant
Location where the document is written.
London
Physical arrangement of a ship’s masts, sails and rigging.
S - Ship
Is the steamer assisted by sail?
No
A ship’s total internal capacity of a ship measured in register tons from the top of the floors to the tonnage deck.
1935
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
Physical extent of a record.
1
Have you noticed missing or incorrect data or images for this document?