Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
06/07/1928
The year in which a vessel’s construction is completed.
1928
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Cammell Laird & Co
The port or place in which the vessel’s construction took place, at the time of writing.
Birkenhead
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
94000
The listed port to which a given vessel belongs.
Liverpool
The date of first visit by a surveyor.
16/09/1927
The individual and/or organisation listed
The Charente Steamship Co Ltd
Location where the document is written.
Liverpool
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
+LMC 7,28; CL; Elec Light
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Type and configuration of the engine(s) supplied for a vessel.
Triple Expansion - Reciprocating
Date in which construction of a vessel’s engines were completed.
1928
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
The official record pronounced by the Committee
Broken up
Recorded date for the vessel’s loss or disposal.
20/09/1959
Pertinent, useful or interesting recorded content.
Also refers to vessel Logician
Name of ship as recorded on the record
Tactician
The process of transferring a vessel to water, but not necessarily her completion.
22/05/1928
Unique identifier for a given ship, it is assigned by a builder.
935
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Liv
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
4 Report on Steam Reciprocating Engine Machinery
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
Y
The date of last visit by a surveyor.
02/07/1928
Name of the individual/entity/organisation responsible for authoring the record
J E Milton; W S Shields
Location where a vessel’s survey was undertaken.
Birkenhead
Date of the meeting of the Classing Committee.
13/07/1928
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
5887
Location of construction for a vessel’s engines.
Birkenhead
Cammell Laird & Co Ltd
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Contextual information related to the reasons of the vessel’s loss or disposal.
Sold for Breaking up, Demolition Commenced
Physical extent of a record.
1
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.