Document
Document
  • Related documents Related
  • Full details Details
  • Report document? Report?
?

Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.

Date recorded as the time of writing.

Date of document

27/04/1929

The year in which a vessel’s construction is completed.

Year of ship completion

1929

The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.

Shipbuilder

John Readhead & Sons Ltd

The port or place in which the vessel’s construction took place, at the time of writing.

Place of build

South Shields

Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.

Document identity

GR130 Vessels of 100 tons & upwards

Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.

First entry?

N

The individual and/or organisation listed that is responsible for the everyday management of a ship. This may be the same as the owner.

Ship manager

Frank Clarke Strick

Broad categories and subdivisions of vessels related to their purpose or function.

Ship type

Cargo

A vessel’s means of propulsion.

Propulsion

Steam

Is the steamer assisted by sail?

Sail assisted steamer

No

Type and configuration of the engine(s) supplied for a vessel.

Engine type

Reciprocating Triple Expansion Direct Acting Inverted Cylinders

Date in which construction of a vessel’s engines were completed.

Year of engine build

1929

Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.

Refrigeration machinery fitted for cargo purposes?

No

Does the vessel possess an auxiliary power source?

Auxillary

No

Is electric lighting fitted to the vessel?

Electric light fitted?

No

A vessel’s calculated maximum speed.

Speed (knots)

1929

Physical extent of a record.

Number of parts

1

Name of ship as recorded on the record

Ship name

Brika

The process of transferring a vessel to water, but not necessarily her completion.

Launch Date

26/03/1929

Unique identifier for a given ship, it is assigned by a builder.

Yard no

495

Previously referred to as signal letters (c.19th C), radio call signs enable a ship to communicate and are assigned by the International Telecommunications Union (ITU).

Signal letter/Call sign

LDGM

The port in which a vessel is registered or permanently based.

Port of registry

Swansea

The individual and/or organisation listed

Ship owner

La Tunisienne Steam Navigation Co Ltd

Location where the document is written.

Location of Document Creation

Swansea

Physical arrangement of a ship’s masts, sails and rigging.

Rig

Sr - Schooner

Predominant material(s) utilised in a vessel’s construction.

Material of construction

Steel

A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).

Gross Register Tonnage

4412

Location of construction for a vessel’s engines.

Location of engine build

South Shields

Engine builder as written

John Readhead & Sons Ltd

Is machinery fitted at the aft of the vessel?

Machinery aft?

No

Generally a smaller additional auxiliary boiler (often used while the vessel is at port).

Is a donkey boiler fitted?

No

Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.

Lloyd's Proving House?

No

Draft

1929

Report an issue with this document

Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.